1.Insertion Type
The hole for the post should be made in advance and distance of every one is in line with one of posts on the sheet. The size of hole is 250X250X400(Lenght X Width X Depth) mm (P.S.the size is just for ground).If you want to adopt the way of installation about the concrete base, its size is 120X120X400(Lenght X Width X Depth) mm. Panel must be installed with post synchronously and when everything is ready, you can just pour concrete directly.
2.The way of welding or connecting bolt
The post and basement can be combined in a way of welding or connecting bolt. The basement should be finished in advance according to the drawing sheet before installation. To make every basement even and distance of each other the same. Furthermore,bolt is stainless steel and anti-theft to make products safe and anti-theft.
|